AZERBAIJAN
Shahdag Winter Tourism Complex Project Phase 1&2
•HOTELS, SKIING SLOPES, RIVER ENGINEERING, WATER DERIVATION WORKS, SNOW PRODUCTION SYSTEM, ENERGY AND WORKSHOP BUILDINGS
•COMMENCEMENT DATE : JUNE 2010
•DATE OF DELIVERY: DECEMBER 2014
EMPLOYER : MINISTRY OF TOURISM
TANZANIA
Dar Es Salaam-Morogoro Railway Project
• START DATE: MAY 2017
• FINISH DATE: MAY 2020
• CONTRACT: FIDIC YELLOW BOOK
• EMPLOYER: TANZANIA RAILWAY CORPORATION
• CONTRACTOR: YAPI MERKEZI A.S.
• ENGINEER: KORAIL JV
TECHNICAL FEATURES:
• 202 KM STANDARD GAUGE RAILWAY PROJECT
• 160 KM/HR DESIGN SPEED
• 6 STATIONS
• 460 CULVERTS
• 96 BRIDGES
• OVER 40 MILLION CUBIC METER EXCAVATION
TURKMENISTAN
Mary 1574 MW Combined Cycle Power Plant
•CAPACITY: 1.574 MW
•EQUIPMENT: 4XSINGLE-FUEL GE F.03 MULTI-SHAFT GAS TURBINES + 4 X HP-LP HRSG + 2 X STEAM TURBINES
•COMMENCEMENT DATE: JULY 2015
•DATE OF DELIVERY: DECEMBER 2018
•EMPLOYER: MINISTRY OF ENERGY, TURKMENISTAN
•SCOPE: LUMP SUM TURNKEY EPC PRIME CONTRACTOR
•CONTRACT: FIDIC SILVER BOOK
Watan 254 MW Simple Cycle Power Plant
•CAPACITY: 254 MW
•EQUIPMENT: 2 X GE 9E PG9171
•COMMENCEMENT DATE: JANUARY 2015
•DATE OF DELIVERY: JUNE 2016
•EMPLOYER: MINISTRY OF ENERGY, TURKMENISTAN
•SCOPE: LUMP SUM TURNKEY EPC PRIME CONTRACTOR
•CONTRACT: FIDIC SILVER BOOK
Derweze 504,4 MW Simple Cycle Power Plant
•CAPACITY: 504,4 MW
•EQUIPMENT: 4 X GE PG9171-B (FRAME 9E)
•COMMENCEMENT DATE: JULY 2013
•DATE OF DELIVERY: SEPTEMBER 2015
•EMPLOYER: MINISTRY OF ENERGY, TURKMENISTAN
•SCOPE: LUMP SUM TURNKEY EPC PRIME CONTRACTOR
•CONTRACT: FIDIC SILVER BOOK
Ahal-2 252,2 MW Simple Cycle Power Plant
•CAPACITY: 252,2 MW
•EQUIPMENT: 2 X GE 9E PG9171
•COMMENCEMENT DATE: JULY 2013
•DATE OF DELIVERY: DECEMBER 2014
•EMPLOYER: MINISTRY OF ENERGY, TURKMENISTAN
•SCOPE: LUMP SUM TURNKEY EPC PRIME CONTRACTOR
•CONTRACT: FIDIC SILVER BOOK
Urban Energy Infrastructure Reinformcement Project in Ashgabat Phase 2 & 3
•TRANSFORMER SUBSTATIONS: 5 PIECES OF 110 KV, 6 PIECES OF 220 KV, 18 PIECES OF 35 KV, 43 PIECES OF 10 KV
•CABLING WORKS: 0,95 KM 220 KV, 22,43 KM 220 KV OVERHEAD LINE, 8,45 KM 110 KV, 27,2 KM 110 KV OVERHEAD LINE, 93 KM 35 KV, 2,35 KM 35 KV OVERHEAD LINE, 418,72 KM 10 KV
•MONITORING AND MANAGEMENT SYSTEM: SCADA AND CONTROL FACILITIES
•COMMENCEMENT DATE : AUGUST 2014
•DATE OF DELIVERY: OCTOBER 2016
EMPLOYER : CITY MUNICIPALITY OF ASHGABAT